Sunday, November 11, 2012

The Build - Wk 42-44

The deck has been completed and looks fabulous! The warm colour of the timber has really lifted the building. The rock wall for the fire place continues to be built, however as the concrete needs to dry in layers, the progress is relatively slow. The wardrobes have been fitted and look really professional.
 
Jobs for next week include the tiler coming out to commence waterproofing the floor and hopefully lay the slate in the sunroom. Other floor coverings have been ordered, but take two weeks to come from the mainland, but at least the choices have been made!