This week all the remaining house
rafters went up, along with the rafters for the carport. The beam around the outside posts got put on
and bolted into place. Blocking out
between the roof rafters at the perimeter of the house was done and along with the
cement sheeting for fireproofing. Also
Ray moved all the clay that we will use in rendering onto big sheets of plastic
for it to dry out. We think there is
around 60 tons of clay! That’s a lot of
rendering….
Coming up next week will be all
the preparation work to enable the tin roof to go up the week after.